Residential Projects

Project: Lalav Airport View, 5 Bldg. 3B+G+F+20+R
Scope: Structural Design including execution of 105 PT slab
Total PT works: 99,000m2
Total built-up area: 147,000m2
Location: Erbil – Iraq
Status: Structural Works Completed

 

Project: English Tower (5B+G+2M+37+R)
Scope: Structural Design – First Concept (Rev.01) Location: Erbil – Iraq Status: Under Construction
Project: Suli View, 5 buildings, 4B+G+M+24+R
Scope: Structural Design and value engineering
Location: Sulaymaniyah- Iraq
Status: Under Construction (2 buildings)

 

Project: Lana City
Description: Lana City Project contains 519 houses, and 5 buildings each of the buildings are 10 floors
Scope: Structural Design of all buildings and houses
Total built-up Area: 250,000m2
Location: Erbil – Iraq
Status: Completed
Project: Rasan Towers (3 No.) Project, 2B+G+F+20TYP+Roof
Scope: Structural Design
Total Built-Up Area:134,880m2
Location: Erbil- Iraq
Status: Under Construction

 

Project: 101 Complex Twin Towers 3B+G+F+S+TH+34TYP+ROOF 
Description: Complex twin towers connected at PT floors (F15, F16, F25, F26)
Scope: Structural Design
Total built-up Area: 90,000m2
Location: Erbil – Iraq
Status: Under Construction

 

Public Buildings

Project: Judicial Council of Erbil, G+2+R
Scope: Structural Design
Total built-up area: 23,000m2
Location: Erbil – Iraq
Project: Darman Hospital, 2B+G+9+R
Scope: Structural Design
Location: Erbil – Iraq
Status: Under Construction
Project: Erbil Governorate, G+3+R
Scope: Structural Design
Total Built-Up Area: 56,500m2
Location: Erbil – Iraq
Status: Under Construction
Project: Haj Osman Mosque
Scope: Structural Design
Location: Erbil – Iraq
Status: Completed

Commercial Buildings

Project: Anzu Headquarter G+3+R
Scope: Structural Design of 3-PT slab (20×20)m
Location: Sulaymaniyah – Iraq
Status: Under Construction

UAE - Post Tension Projects

The following Projects were designed and supervised by Dr. Kamaran, during the period from 2008-2010 in UAE

Project: Rufi Park View 2B+G+14+R+UR
Scope: Post-Tension Slab Design and Supervision (17 slabs)
Location: Dubai Sports City, Plot No. 682-1376
Consultant: Dartin Engineering
Contractor: Majid Hilal Contracting
Built up Area: 22,000m2
Status: Completed 2011
Project: Residential Building B+G+14+Gym+R
Scope: Post-Tension Slab Design and Supervision (16 slabs)
Location: Tecom – Dubai, Plot No. C-005-003
Consultant: Al Khawaja Consultant
Contractor: Al Badr Contracting
Built up Area: 22,230m2
Status: Completed 2010
Project: Residential Building 2B+G+4+R
Scope: Post-Tension Slab Design and Supervision (6 slabs)
Location: JAFZA, Plot No. JVT-04
Consultant: Dartin Engineering
Client: Anis Property investment
Built up Area: 12,320m2
Status: Completed 2011
Project: Residential Building B+G+4+R
Scope: Post-Tension Slab Design and Supervision (7 slabs)
Location: Al Karama-Dubai, Plot No. 318-862
Consultant: Al Ajmi Consultant
Contractor: Al Baraha Land Contracting
Built up Area: 4,920m2
Status: Completed 2009
Project: Residential/Commercial G+13+Gym+R
Scope: Post-Tension Slab Design and Supervision (15 slabs)
Location: Al Mamzer – Dubai, Plot No. 134-1039
Consultant: Arif & Bintoak
Contractor: Eastern International
Built up Area: 33,000m2
Status: Completed 2010
Project: Residential B+G+5+R
Scope: Post-Tension Slab Design and Supervision (7 slabs x 2 parts)
Location: Al Warqaa 1st – Dubai, Plot No. 421-0699
Consultant: Fraser Nag Partnership
Contractor: Al Amar Contracting
Built up Area: 16,212m2
Status: Completed 2008
Project: Commercial 3B+G+M+3
Scope: Post-Tension Slab Design and Supervision (7 slabs)
Location: Al Garhoud – Dubai, Plot No. 214-270
Consultant: Ziki Homsi Consulting
Contractor: Majid Hilal Contracting
Built up Area: 10,500m2
Status: Completed 2010
Project: Shami Tower, Residential 2B+G+17+R
Scope: Post-Tension Slab Design and Supervision (21 slabs)
Location: Sport City – Dubai, Plot No. 682-1367
Consultant: Dartin Engineering
Contractor: Majid Hilal Contracting
Built up Area: 36,858m2
Status: Completed 2012
Project: Arena Apartments, G+11+HC+S.Pool
Scope: Post-Tension Slab Design and Supervision (12 slabs)
Location: Sport City – Dubai, Plot No. 682-757
Consultant: Adnan Saffarini
Contractor: Al Ghaith Contracting
Built up Area: 21,588m2
Status: Completed 2009
Project: Residential 2B+G+12+Gym+R
Scope: Post-Tension Slab Design and Supervision (14 slabs)
Location: Al Nahda 2- Dubai, Plot No. 241-456
Consultant: High Art Engineering Consultant
Contractor: Julfar Contracting
Built up Area: 8,200m2
Status: Completed 2011
Project: Zumurruda Tower, B+G+11+R
Scope: Post-Tension Slab Design and Supervision (14 slabs)
Location: Al Nahda Second – Dubai, Plot No. 241-433
Consultant: Al Shurooq Engineering
Contractor: Julfar Contracting
Built up Area: 12,750m2
Status: Completed 2010
Project: Commercial/Offices 2B+G+8+R
Scope: Post-Tension Slab Design and Supervision (11 slabs)
Location: Nad Al Shiba – Dubai, Plot No. 26-061
Consultant: Model Engineering Consultant
Contractor: Mozoon Contracting
Built up Area: 10,530m2
Status: Completed 2010
Project: GEMS Modern School, G+3
Scope: Post-Tension Slab Design and Supervision (5 slabs x 6 phases)
Location: Nad Al Shiba 3 – Dubai
Consultant: Engineering Consultant Group
Contractor: Chicago Maintenance & Contracting
Built up Area: 38,000m2
Status: Completed 2008
Project: Al Shaer Residential Bldg, B+G+12+R
Scope: Post-Tension Slab Design and Supervision (14 slabs)
Location: Al Nahda Second – Dubai, Plot No. 241-389
Consultant: Al Emarah AL Khalijia Engineering
Contractor: Yousuf & Aman Contracting
Built up Area: 9,750m2
Status: Completed 2010
Project: Mirdif Mall, B+G+1+R
Scope: Post-Tension Slab Design and Supervision (3 slabs x 3 Parts),
+reevaluation of a slab due to scaffolding failure during conc. pouring
Location: Mirdif  – Dubai, Plot No. 251-4441
Consultant: Al Ajmi Engineering Consultant
Contractor: Facts Contracting
Built up Area: 5,800m2
Status: Completed 2008
Project: Add. to Villa, B+G+1+R
Scope: Post-Tension Slab Design and Supervision (3 slabs)
Location: Jumeirah Second – Dubai, Plot No. 342-911
Consultant: Al Thuraya Civil Engineering
Client: Juma Suhail
Built up Area: 1,722m2
Status: Completed 2008
Project: Hotel, 2B+G+7
Scope: Post-Tension Slab Design and Supervision (10 slabs)
Location: Al Hamriya- Dubai, Plot No. 313-423
Consultant: Dubai Consultant
Contractor: Al Nekhreh Contracting
Built up Area: 14,000m2
Status: Completed 2012
Project: Sport Tower, B+G+14+SF+HC
Scope: Post-Tension Slab Design and Supervision (17 slabs)
Location: Sport City – Dubai, Plot No. 682-1293
Consultant: Barajeel Engineering
Contractor: Majid Hilal Contracting
Built up Area: 13,500m2
Status: Completed 2012
Project: Emirates NBD Bank, 4B+G+4+R
Scope: Post-Tension Slab Design and Supervision (10 slabs)
Location: Hor Al Anz- Dubai, Plot No. 127-1908
Consultant: Khatib & Alami Consultant
Contractor: Eastern International Contracting
Built up Area: 16,540m2
Status: Completed 2009